Construction dynamics

  • April 2025

    In Sections 1–2, masonry work has begun on the commercial floors. Special attention is being given to the complex arched openings for panoramic windows — a distinctive architectural feature of the complex. Windows have been installed on all floors, and the installation of aluminum façade systems is underway in the penthouses and premium apartments with private patio areas.

    Inside, work is progressing intensively:

    Plastering (Section 2, 3rd–7th floors)

    Installation of high-quality water supply and sewage systems (Section 2, 3rd floor)

    Electrical and low-voltage systems installation is nearing completion — preparations for intercom and internet connections are underway

    The lightning protection system has been installed

    The final stage of smoke extraction and air pressurization ductwork for the underground parking is in progress

    Exterior work (Section 1):

    Drainage systems for air conditioners are being installed

    Preparations for façade lighting installation are underway

    Thermal insulation with high-density mineral wool has begun, with selective use of polystyrene at connection points to enhance waterproofing properties

    🔹 Section 3
    Monolithic works on the parking structure and the first commercial floor have been completed — the section is confidently gaining height.

    Across the site, the project is transforming from blueprint to living space. From heavy machinery to the precision of plasterwork — everything is operating in sync. This step-by-step focus allows us to concentrate skilled teams from section to section without losing momentum.

    While interior work has begun in the initial sections, other parts of the project are quickly rising in scale and height. Here’s what’s new:

    🔹 Section 5

    Monolithic construction of 9 floors completed

    Masonry work is actively progressing, reaching the 6th floor

    🔹 Section 6

    Monolithic works fully completed up to the 9th floor

    Three floors of exterior and interior wall masonry have already been built

    🔹 Section 7

    Monolithic work on the above-ground structure has started

    Two floors of the structure have already been completed

    🔹 Section 8

    Earthworks completed

    Monolithic construction of the foundation and underground level is in progress

    🔹 Section 9

    Excavation of the foundation pit is completed, ready for the start of monolithic construction

    Inner Courtyard

    The area of monolithic paving in front of Section 6 has been expanded, preparing the space for a future cozy courtyard

    Underground Parking

    Soil and gravel base is being compacted in preparation for the lean concrete layer

    Water inlets for the fire suppression system are being installed

  • October 2024

    Monolithic works have been completed on the 8th and 9th floors of Sections 1 and 2, with final construction works on the monolithic roof structures currently underway.

    Masonry work using ceramic blocks for the exterior and load-bearing walls has been completed on the 3rd to 5th floors of Section 2 and the 3rd to 4th floors of Section 1. Simultaneously, ventilation shafts are being installed using block elements.

    Work continues on expanding the storage area for construction materials through land clearing and leveling.

    Earthworks are ongoing on the site of Section 3 in preparation for the excavation pit.

    In Sections 5 and 6, construction of monolithic structures on the 1st and 2nd floors is in progress.

  • September 2024

    The first two sections have reached the final stages of monolithic construction work.
    On the 3rd and 4th floors, masonry work is ongoing for the exterior and load-bearing walls using ceramic blocks, and ventilation shafts are being installed using block elements. Preparatory work for facade insulation is also underway.

    In the fifth section, the main structural construction is in an active phase. Meanwhile, in the sixth section, the parking structure has already been completed, allowing the project to move on to the next stages of construction.

  • June 2024

    Excavation work was carried out, which included removing the topsoil, forming a pit according to the design parameters, as well as removing and transporting waste material.

  • March 2024

    Installation of steel structures, placement of reinforcement meshes in the frame to ensure strength and durability, pouring concrete around the reinforcement to form monolithic structures of sections 1 and 2.

  • December 2023

    Preparing the soil for the foundation. Organization of a water drainage system in the pit, which is necessary to ensure water resistance and resistance to groundwater.

  • October 2023

    Excavation work was carried out, which included removing the topsoil, forming a pit according to the design parameters, as well as removing and transporting waste material.

Map

Make a route
  • 5 min to the city center by car min to the city center by car
  • 3 min to the city center by car min to the city center by car
  • 5 min to school by car min to school by car
  • 3 min to Epicenter by car min to Epicenter by car
  • 5 min to kindergarten on foot min to kindergarten on foot

Contact us

We appreciate your interest in our company and are ready to provide you with a comprehensive answer. Our specialists are already working on this, and we will contact you shortly.

    We appreciate your interest in our company and are ready to provide you with a comprehensive answer Our experts are already working on this, and we will contact you shortly.

    Sales Department