Construction dynamics
- May 2025
In Section 1, the first facade window systems have been installed in the penthouses. Two facade sides have been insulated.
In Section 2, plastering work has been completed on all floors. Installation of water supply and sewage systems has been completed on five floors — each apartment is now connected to the water supply and sewage risers have been installed.
In Section 3, monolithic works have reached the third floor.
In Section 5, facade masonry works are nearing completion. Preparations are underway for the installation of window systems.
In Section 6, exterior and interior wall masonry is in progress on the 7th floor.
In Section 7, monolithic works have reached the 4th floor.
In Section 8, foundation pouring and backfilling have been completed.
- April 2025
In sections 1–2, masonry work has begun on the commercial floors. Windows have been installed on all levels, and installation of aluminum façade systems in the penthouses is ongoing.
Electrical and low-voltage systems installation is nearing completion — preparations are underway for intercom and internet connection. Ventilation ductwork for smoke extraction and air pressurization in the underground parking is in its final stage.In section 3, monolithic work on the parking and the first commercial floor has been completed — the section is steadily rising.
In sections 5 and 6, the monolithic structure up to the 9th floor has been completed, and wall masonry is actively underway.
In section 7, monolithic work on the 2nd floor has begun.
In section 8, earthworks have been completed, and monolithic structures for the foundation and underground level are in progress.
Excavation for section 9 has been completed. - October 2024
Monolithic works have been completed on the 8th and 9th floors of Sections 1 and 2, with final construction works on the monolithic roof structures currently underway.
Masonry work using ceramic blocks for the exterior and load-bearing walls has been completed on the 3rd to 5th floors of Section 2 and the 3rd to 4th floors of Section 1. Simultaneously, ventilation shafts are being installed using block elements.
Work continues on expanding the storage area for construction materials through land clearing and leveling.
Earthworks are ongoing on the site of Section 3 in preparation for the excavation pit.
In Sections 5 and 6, construction of monolithic structures on the 1st and 2nd floors is in progress.
- September 2024
The first two sections have reached the final stages of monolithic construction work.
On the 3rd and 4th floors, masonry work is ongoing for the exterior and load-bearing walls using ceramic blocks, and ventilation shafts are being installed using block elements. Preparatory work for facade insulation is also underway.In the fifth section, the main structural construction is in an active phase. Meanwhile, in the sixth section, the parking structure has already been completed, allowing the project to move on to the next stages of construction.
- June 2024
Excavation work was carried out, which included removing the topsoil, forming a pit according to the design parameters, as well as removing and transporting waste material.
- March 2024
Installation of steel structures, placement of reinforcement meshes in the frame to ensure strength and durability, pouring concrete around the reinforcement to form monolithic structures of sections 1 and 2.
- December 2023
Preparing the soil for the foundation. Organization of a water drainage system in the pit, which is necessary to ensure water resistance and resistance to groundwater.
- October 2023
Excavation work was carried out, which included removing the topsoil, forming a pit according to the design parameters, as well as removing and transporting waste material.
Map
Make a route- 5 min to the city center by car min to the city center by car
- 3 min to the city center by car min to the city center by car
- 5 min to school by car min to school by car
- 3 min to Epicenter by car min to Epicenter by car
- 5 min to kindergarten on foot min to kindergarten on foot